Answer:
Answer for Part A and Part B is as follows:
Particulars                         2016 year              2017 year
Contract Price                        $13,00,000            $13,00,000
Cost that has been incurred               $675000             $950000
Estimated cost to complete             $225000                 $0
TOTAL COST Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â $900000 Â Â Â Â Â Â Â Â Â Â Â Â Â Â $950000
Expected Gross profit                   $400000             $350000
Percentage that is completed          75 percent            100percent
Gross profit to be recognised             $300000            $50000
Note: Calculations have been made according to the data and figures given in the question.